Migrating an existing on-premises BMC Helix ITSM system to an upgraded on-premises BMC Helix system
This section describes the procedure to migrate from an existing version of BMC Helix IT Service Management (BMC Helix ITSM) on-premises to an updated version of BMC Helix ITSM on-premises.
To upgrade your existing BMC Helix ITSM and associated Service Management applications to BMC Helix ITSM containerized platform, you perform the following actions:
- Perform an installation of an out-of-the-box BMC Helix ITSM platform and the applications that you want to install.
- Migrate your workflow customization and overlays.
- Test the migrated data.
- Migrate your BMC Helix ITSM data from your current production environment to your new environment by using BMC Helix Data Manager.
Supported versions for data migration
The following table lists the supported source and target product versions to migrate data:
Application | Source version | Target version |
---|---|---|
BMC Helix ITSM | 20.02 and later To upgrade to version 21.3.06 or 22.1.06 from BMC Helix ITSM versions 8.1, 9.1, 18.05, 18.08, 19.02, and 19.08, see BMC-Helix-Data-Manager-support-guidelines | 21.3.06, 22.1.06 |
BMC Digital Workplace | 20.02 and later | 21.3.06, 22.1.06 |
BMC Digital Workplace Catalog | 20.02 and later | 21.3.06, 22.1.06 |
BMC Helix ITSM: Smart IT | 2.0 and later | 21.3.06, 22.1.06 |
BMC Helix ITSM: Smart Reporting | 20.02 and later | 21.3.06, 22.1.06 |
Supported Databases
Source databases | Target databases |
---|---|
PostgreSQL, Microsoft SQL, Oracle | PostgreSQL, Microsoft SQL, Oracle |
An overview of the different phases of the process is shown in the following image:
Before you begin
Complete all the premigration tasks for the on-premises to on-premises upgrade and data migration. For more information, see Preparing for upgrade.
- We recommend that you complete the following training course to successfully use BMC Helix Data Manager:
End-to-end upgrade process for BMC Helix ITSM on-premises version
The following table provides a sequence for your system administrator to upgrade your existing platform and applications:
Phase | Key activities | Milestones |
---|---|---|
| Get the infrastructure for setting up your systems. | |
| Setup all the required systems and get data ready for migration. | |
| Migrate all your data and perform system testing. | |
| UAT is the sign-off of the system. | |
| Go live on your new production system. |