Planning activity dates

You should enter the Scheduled Start Date and Scheduled End Date for the activity. The Dates tab in the Activity form includes various fields where you can enter scheduling information, for example, the actual start date of the activity.

To plan dates for activities

  1. Open the activity.
  2. Click the Dates tab.
    Scheduled tasks are displayed.

  3. In the Activity Datesarea, specify the following values to assign the activity:
    • Scheduled Start Date — Optionally, enter an estimated start date.
    • Scheduled End Date — Optionally, enter an estimated end date.
      You should set the start date and end date to be different from the dates of the parent release.
  4. Save the activity.
Was this page helpful? Yes No Submitting... Thank you

Comments

  1. Jess Bugarin

    If the Activity Scheduled End Date is after the Release Scheduled End Date, the user is given ARWARN 45747 letting them know this is the case. Where can I manage this warning? I can't find it in the Administrator Console. Do I have the ability to change it from a warning to an Error to prevent the Activities from being outside of the scheduled dates for the release?