Go live activities during staged upgrade


As part of the go-live process for a staged upgrade, you must perform the following tasks:

  1. Remove the production URL from maintenance mode, and ensure that is in admin-only mode. 
  2. Reboot all the BMC Remedy AR system servers and BMC Remedy Mid Tier virtual machines.
  3. Update your authentication settings. 
  4. If you are using LDAP, test the VPN.
  5. Validate the integrations are actively working. 
  6. Revert all the server configuration changes you have applied on the source server and the destination server.
    See Performing-server-configuration-adjustments.
  7. Revert the standard parameters settings you performed during pre-cutover.
  8. Set the server group rankings.
  9. Restart the BMC Remedy AR System service.
  10. Update the destination server names.
    See Updating-the-destination-server-names-after-data-migration.  
  11. Review the issues identified during UAT.
  12. Remove the production URL from admin-only mode.
  13. Enable and restart email services.
  14. Restart the BMC Remedy AR system service.

 

 

 