Troubleshooting Smart IT change calendar
Issue symptom
The Smart IT change calendar does not load.
Issue scope
- In a server group environment, the Smart IT change calendar does not open in one or more servers.
- More than one change requests that have the same scheduled dates are associated to the same CI.
Diagnosing and reporting an issue
Task | Action | Steps |
|---|---|---|
1 | Enabling the network logs | Open the Developer tools by using either Internet Explorer 11 or Google Chrome. To enable the network logs in Internet Explorer 11
To enable the network logs in Google Chrome.
|
2 | Enabling the debug mode in Smart IT | For instructions, see BMC communities. |
3 | Enabling the server-side AR system logs | For instructions, see Enabling logs for performance issues. |
4 | Validating the Smart IT change calendar configuration |
|
If you upgrade Smart IT, you can access the logs by performing the following steps:
- In Internet Explorer 11:
- From the Tools menu, select F12 Developer Tools.
- Click the Console tab.
- In Google Chrome:
- Go to Customize and control Google Chrome > More tools > Developer tools.
- Click the Console tab.
In the logs, look for the following error that might occur after after you upgrade Smart IT. To resolve this issue, see Resolution for HTTP Error 500.
Resolutions for common issues
Symptom | Action | Reference |
|---|---|---|
Smart IT change calendar does not load and keeps spinning. |
| |
Smart IT calendar does not load and throws the following error: HTTP Error 500 | This error occurs because the JAR file from the earlier release exists in the Smart IT directory location. Perform the following steps to resolve the issue:
| |
When you try to open Smart IT change calendar, you experience performance issues. | This issue occurs because two or more change requests are associated to the same CI and have the same scheduled dates. To resolve the issue, add new indexes in the following forms:
| |
When you set the disableCollisionsManagement parameter to true, it still triggers a REST call for a collision. | Apply Smart IT 20.02 HF9 or the latest hotfix version available. | |