Managing the relationship between change requests and incidents
In BMC Helix ITSM you can perform certain tasks when working with incidents related to change requests.
To define an incident related to a change request
- Open the change request.
- Click on the Related items tab.
- Select Create related > Incident.
- Enter the values in the incident.
- Click Save.
To relate an incident to a change request
- Open the change request.
- Click on the Related items tab.
- Select Relate existing item > Incident.
- In Relate items, search for the required incident.
- Select the incident.
- From the Relationship type, select the value that relates the incident to the change request.
For example, if the incident was caused by a change that was introduced by a change request, select Caused or if the change resolves the incident, select Corrects. - Click Save.
To unrelate an incident from a change request
- Open the change request.
- Click on the Related items tab.
- select the incident record that you want to unrelate.
- click Delete.
- Click Yes on the Confirmation Dialog box.
Instructions for classic interfaces
Tip: For faster searching, add an asterisk to the end of your partial query. Example: cert*