Including autocost estimates in a change request
In , you can include autocost estimates in a change request.
To use autocost estimates
- Open the change request in the Change form.
- From the left navigation pane, select Links > Financials.
- In the Calculation Unit Type, select Flat Rate, Hours, or Minutes.
- In the Budget Estimated Total Time, enter the time based on unit type.
Use this information to forecast the cost. For example, you can budget that the change will take two hours to perform. - In the Actual Total Time, enter the time according to the calculation unit type.
Enter this information after the change is completed (for example, you budgeted two hours to do the change but it took three hours). - Save the change request.
If a matching cost rate is found, a cost is generated.