Configuring the disaster recovery system (Sybase)


This section explains the steps you must perform to configure the disaster recovery system for the servers that run Infrastructure Management.

Note

BMC recommends that you validate these recommendations before you actually implement them in a production environment.

Process for configuring the disaster recovery system

dr_sybase.png

Step

Task

Reference

1

On the DNS server, set an alias name for the primary BMC TrueSight Infrastructure Management Server.

2

Configure the primary BMC TrueSight Infrastructure Management Server.

3

Configure all the remote event cells.

4

Configure the recovery BMC TrueSight Infrastructure Management Server.

Configuration scenario for a disaster recovery system

The following scenario explains the disaster recovery setup on which these best practices are based:

  • Calbro Services has several branch offices across the world. It has its primary Infrastructure Management Server located in Amsterdam, Netherlands. It has its recovery Infrastructure Management Server in New York, United States of America, on a different network.
  • Calbro Services wants its server in New York to be up and running whenever its primary Infrastructure Management Server at Amsterdam fails. Calbro Services also wants its primary Infrastructure Management Server to resume services after the issue has been fixed. It also uses a DNS server that resolves to the recovery Infrastructure Management Server at the time of a disaster. Both of the servers run Infrastructure Management as a standalone installation.

The following names are assigned to the servers:

Servers

Name

Primary Infrastructure Management Server at Amsterdam

amsterdam.calbro.com

Recovery Infrastructure Management Server at New York

newyork.calbro.com

Alias name to be set for the primary and recovery Infrastructure Management Servers

pronet

Assumptions to configure a disaster recovery system for Infrastructure Management

The configuration settings to achieve a disaster recovery system for your Infrastructure Management environment are based on the following assumptions:

  • Your system uses two standalone BMC TrueSight Infrastructure Management Servers located at two different geographic locations or data centers.
  • No data changes will be made to the BMC Atrium Configuration Management Database, BMC UDDI registry server, or BMC BladeLogic Service Automation during disaster recovery operation. If data changes are made during the disaster recovery operation, then the common data will become out of sync between these products and their integrated BMC TrueSight Infrastructure Management Servers.
  • BMC TrueSight Infrastructure Management Servers must be on different networks.
  • Your system uses a Domain Name System (DNS) alias name.
  • Your system has the routing and firewall settings properly configured.
  • Your system has only one BMC TrueSight Infrastructure Management Server running at any given time.

Related topics

Disaster-recovery-deployment-architecture-Sybase

Bringing-up-the-recovery-or-primary-Infrastructure-Management-Server-Sybase-after-a-disaster

Worksheet-for-configuring-a-disaster-recovery-system-for-Infrastructure-Management-Sybase

 

Tip: For faster searching, add an asterisk to the end of your partial query. Example: cert*