Upgrading an ETL package


This topic describes the steps to upgrade an ETL module that has already been activated. This may be necessary in different situations. For instance:

  • You encountered problems while activating the project.
  • An issue was detected after a module was activated.
  • An improved module is available.

If you create a new workspace in Integration Studio, import the new project template, and try to activate it again, you will get an error such as: Another module with file name <ETLname> already exists in production.

1_ETLPACK.png

The following procedure describes a workaround that prevents the error.

  1. Refresh the TrueSight Capacity Optimization repository.
    1bis_ETLPACK.png

  2. Download the original module project from BMC TrueSight Capacity Optimization. From the Capacity Optimization Repository, right-click on the desired project, and click Download project.
    2_ETLPACK_S.png

  3. Select the folder where the project will be downloaded.
    2bis_ETLPACK.png

    Warning

    Note

    If you want to keep a copy of the ETL project on your disk, do not overwrite it. Repeat the procedure, and select a different download folder.

    2tris_ETLPACK.png

  4. After the download has completed, right-click the project name in the Package Explorer tab and click Import.
    3_ETLPACK.png

  5. In the pop-up window that appears, click General > Archive File > Next.
    4_ETLPACK.png

  6. Select the archive for the new module (for example, myETL.zip), clear the Overwrite existing resources without warning option, and click Finish.
    5_ETLPACK.png

     All the new archive files are imported into the existing project.
    6_ETLPACK.png

  7. Click Yes to overwrite all the original files except project.xml, to retain the original projectid.
    7_ETLPACK.png

  8. After the import procedure is complete, right-click on the project name and click Close Project.
    8.png

  9. Right-click on the project name, and click Open Project to refresh all the project information.
    9.png

  10. Activate the module. For more information, see Activating-a-custom-parser-module or Activating-a-custom-extractor-module.

 