Reassigning change requests

You or your manager can reassign the change request to another change coordinator.

For more information on reassigning change requests, see Working with change request assignments.

To reassign a change request yourself

  1. Open the change request in the Change form.
  2. Use one of the following to select who should be reassigned to the change request.

    When using the Best Practice view

    When using the Classic view

    In the change form select the Coordinator Group and Change Coordinator. On the Work Detail tab select a Manager Group and Change Manager

    On the Assignment tab, select to whom to assign the change request.

    Note

    If the Change request is in the Planning in Progress stage, you must be the Change Manager or have Change Manager permissions to reassign the change.

  3. Click Save.
    The Change Manager or Change Coordinator is notified of the reassigned change request.