Scheduling holidays
To set holiday times
- Open the Business Time Holidays form.
- Click the Holiday Definition tab.
Business Time Holidays form In the Schedule Name field, enter the unique identifier for this holiday schedule.
Use this identifier to reference this schedule in all business hours calculations.- In the Holidays field, list the holidays that make up the holiday schedule.
Enter holiday time as:
date,startTime,endTime
For example:
07/4/09,9:00:00 A.M.,5:00:00 P.M.
is a holiday that starts at 9:00:00 A.M. on 7/4/09 and ends at 5:00:00 P.M. on the same day.- To separate the dates, press Enter or insert semicolons between the dates.
- The number of dates that can be specified in this list is unlimited.
The holiday entry cannot span across midnight, and the Start time must be less than the End time. - Holiday time uses the offset hours from the Workday schedule.
Only short date/time format is supported in the Business Time Holidays form. Long-date formats (such as January 1, 2005) are not supported. - The dates are interpreted on the server and follow the server's formatting rules.
- If clients are configured for other date formats and the dates entered in the Business Time Holidays form are entered in a client format incompatible with the server format, they are not correctly interpreted as holidays, or they might be interpreted as a different day than was planned.
- The ARDATE format is not supported in Business Time Holidays form.
- Click the Administrative Information tab.
The Holiday ID field contains the AR System ID for this schedule. The Change History field is used to track structural or administrative changes to the schedule. - In the Help Text field, enter the purpose of the schedule.
- Save the form.