Creating a change request
If infrastructure change is required to permanently resolve the incident request, assign the incident request to a Change Coordinator. For information about how to reassign a ticket to a Change Coordinator this, see Reassigning incident requests. If you have the correct change management permissions, you can create a change request from the Incident Request form. If you are not sure about your change management permissions, ask your system administrator.
To create change from an incident
- Open the incident request record.
Create the change request from the incident request.
- From the Quick Actions area, click the arrow beside Create Related Request.
- From the menu, select Infrastructure Change.
A Change Request form appears. The Product and Operational Categorization are copied from the incident to the infrastructure change. A relationship is created between the change and the incident.
If you want to create the related change request by using a change template, then you must first apply the template and then create the relationship. The relationship is not created if this sequence is not followed.- Complete the Change Request form.
For information about creating change requests, see Initiate stage - Creating change requests. - Click Save.