Planning milestone - Planning and scheduling the release request


After a release request is approved at the Planning Approval phase, the release coordinator must plan the details associated with the release.

g_rm-plan_61571_516.gif

Plan for the following important details:

  • Set the release request's status to Planning, and review the planned dates.
  • Estimate the time the project will take.
  • Estimate any applicable downtime associated with the release request.
  • Register an available or unavailable time segment to perform the release.
  • Assess the risks and impact of the release request.
  • Specify the business justification for the release (if this was not already done when the release request was created).
  • Create your plans.
  • Calculate the costs associated with the release request.
  • Submit the release request for approval.
     Approvers require this information to be able to decide whether to approve or reject the release request.

To plan and schedule the release request

  1. Open the release request at the Planning In Progress status.
  2. Open the Calendar.
  3. Choose Quick Action > View Calendar.
  4. Select how many days' worth of requests and business events to show.
  5. Select Release Requests to view release requests in the calendar.
  6. Select the requests and business events for a specific day. 
  7. Close the Change Calendar when you are finished.
     For more information, see Using-the-Calendar.
  8. Register available or unavailable time segments for your business event, operational categorization, or CI.
     For more information, see Using-Schedule-Assist-to-search-for-available-times.
  9. Click the Date/System tab.

    rf-dates_61467_516.gif
    When planning a release request, you use this tab to track the scheduled, actual, and deployment start and end dates of releases.
  10. Revise the start and end dates as needed.
  11. Review the Business Justification field on the Release form.
    For more information, see Specifying-the-business-justification.
  12. (Optional) Choose Links > Financials.
    You can calculate the costs associated with the change request.
     For more information, see Close-Down-milestone-Completing-release-requests.
  13. Save your work.
  14. Use the Process Status Flow area to move the release request from the Planning In Progress status to the Build Approval phase.
     The release must be approved before it can move forward.