Managing the effort log


In addition to creating a track effort log entry, you can modify or delete an effort log. You can also update the assignee effort duration in the effort log.

Important

You must be the change manager or the change coordinator to modify the effort time.

To modify the effort log

  1. From the change request, choose Functions > Track Effort.
  2. To delete the effort log, select an entry and click delete.
  3. To update assignee effort duration, select the entry and enter the time spent in hours or minutes.
  4. To modify the effort log, select a record from the table and click View.
  5. Update any of the assessment type information and the time spent.
  6. Click Save.

 