Information
This documentation supports the 20.02 version of Remedy Asset Management.To view an earlier version, select the version from the Product version menu.

Changing the status for a schedule


After you complete scheduled activities for a maintenance schedule or audit schedule, you must change the status of the schedule to Completed. Any user can change the status of a schedule.

Warning

Important

You can add only the following CI types to a schedule:

  • Application
  • Application Infrastructure
  • Application System
  • Computer System
  • Mainframe
  • Printer
  • Software Server
  • Equipment

To change the status for a schedule

  1. Open a CI, as described in Using-search.
  2. From the navigation pane, choose Functions > Schedule.
     This option is displayed only for valid CI types.
  3. In the Schedule Information dialog box, select the schedule that you want to modify, and click View.
  4. In the Schedule Information form, in the Status field, select a new option.
     The options are Scheduled, In Progress, and Completed. After you complete activities for a maintenance schedule or an audit schedule, change the status to Completed.
  5. Click Save.
  6. In the confirmation message that appears, click OK.

The modified schedule appears in the Schedule tab on the CI Information form. If you changed the status to Completed, the Schedule Information table displays the next scheduled audit or maintenance date.

 

Tip: For faster searching, add an asterisk to the end of your partial query. Example: cert*

Remedy Asset Management 20.02