Changing project statuses


When a new project is created, by default, its status is set to Draft and only the portfolio manager creator of the project can access the project. Once the project is moved to the 'Plan/Prepare' status, the Project Manager of the project, Portfolio Manager of the portfolio, Project Masters, Portfolio Masters and Project Managers with write addtional access in the project, can move it to different statuses throughout its lifecycle.

image2022-4-26_17-35-46.png

To change a project status

  1. Log in to the Agility Suite application.
  2. Navigate to Workspace > Projects.
  3. To open a project on the Projects workspace, click the required project ID.
  4. On the project details page, click Edit.
  5. Select the required value in the Status field. The following table lists the required status change based on actions you can perform on a project:

    From status

    Action

    Change to status

    Draft


    The project is considered feasible and necessary by the portfolio manager, and a project manager is appointed.

    Plan/Prepare

    The project manager who is assigned to the project wants to cancel the project.

    Cancelled

    Plan/Prepare


    The individual sprints, phases and tasks have been identified, scheduled and assigned by the project manager.

    Task users can start the implementation of the tasks that are assigned to them:

    • For Agile projects, the project manager updates sprints to 'In progress' status. 
    • For Phased projects, the initial phase status is 'Staged' which is changed to 'Active' automatically.

    In Progress

    The project manager assigned wants to cancel the project.

    All sprints, phases and tasks are cancelled automatically when the project is cancelled.

    Cancelled

    In Progress

    The project manager assigned verifies that all sprints or phases and tasks have been completed. 

    Completed

    The project manager assigned wants to cancel the project.

    All sprints, phases and tasks are cancelled automatically when the project is cancelled.

    Cancelled

  6. Click Save.

 