This documentation supports the 25.1 version of BMC Helix ITSM: Service Desk.To view an earlier version, select the version from the Product version menu.

Configuring decision trees


A decision tree takes the user step by step through a questionnaire. Based on the user's answers, the decision tree completes part of the form for a new incident request record by copying blocks of text into the record. Each element in the decision tree displays a list of items. The user's final selection completes part of the incident.

A decision tree is composed of main branches and branches. It might also include branch items. A main branch groups branches and branch items. Branches can group branch items. The main branches are the initial prompts or questions that the user sees. For example, a user might select "Is this a hardware issue?" Based on the reply, the decision tree displays this list: workstation, monitor, and printer issues. When the user selects from a branch, further branch items might be displayed. For example, if the user selects Printer Issues, the incident might be categorized, and the user can select further from this list: paper jam, low toner, and other printing issues.

Following is an example branching structure for a decision tree:

  • Is this a hardware issue? (Main branch)
  • Is this a workstation issue? (Branch 100)
    • Is the workstation unable to boot? (Branch item 101)
    • No power? (Branch item 102)
  • Is this a monitor issue (Branch 200)
    • Does the display flicker excessively? (Branch item 201)
    • No power? (Branch item 202)
    • Picture appears incorrectly? (Branch item 203)

To configure a decision tree

  1. From the Application Administration Console in Mid Tier, click the Custom Configuration tab.
  2. From the Application Settings list, select Incident Management > Decision tree configurations > Decision Tree, and then click Open.
    The Decision Tree form opens in New mode to create a new decision tree. To modify an existing decision tree, select the appropriate decision tree.
  3. From the Company field list, select the appropriate company.
    If the decision tree applies to all companies, leave the default value of Global.
  4. In the Description field, enter a brief description.
    If a system has more than one decision tree, users select the appropriate decision tree by this description.
  5. If appropriate, select a locale.
  6. If the decision tree is not ready to be used, select a status of Proposed or Offline.
    When the decision tree is ready for use, change the status to Enabled.
  7. Click Save.
    You can create branches of the decision tree only after you save it.
  8. Create main branches of the decision tree by performing the following steps for each main branch.
    1. Click New Main Branch.
    2. In the Branch Text field, type the question.
    3. If there are multiple main branches, type or select the appropriate sort order in which the questions appear.
    4. Click Save.
  9. Create branch details to  specify the actions you take to complete the incident form.by performing the following steps for each branch detail.
    1. Select the appropriate main branch, branch, or branch item.
    2. Click New Branch or New Branch Item.
      The Branch Update dialog box appears.
    3. Enter the question or prompt in the Branch Text field.
    4. Enter or select the appropriate sort order.

      Tip

      If you leave gaps in the sort order, it is easier to insert branches later. For example, if you give three branches sort orders of 100, 200, and 300, you can later insert another branch at 150 without renumbering.

    5. Select the appropriate incident action type and specify any required details.

    6. Click Save.
  10. Continue to add main branches, branches, and branch items as required.
  11. Click Save.

 

Tip: For faster searching, add an asterisk to the end of your partial query. Example: cert*