Risk recalculation
In certain scenarios, risks are recalculated because of configuration conflicts. For example, when the user uses a change template that has a risk value defined, the risk level for the change is set to this value. At some point, if this change is reassigned to a user for whom risk settings have been configured, risk is recalculated based on that defined configuration. The value defined in the change template is overwritten and the following error message is displayed:
To configure risk within a change template, select Administrator Console > Application Administration Console > Custom Configuration > Change Management > Template > Template and define a risk level.
To configure risk calculations on the Risk Factor Configuration form, select Administrator Console > Application Administration Console > Custom Configuration > Change Management > Risk Factors > Change Risk Selection and define risk calculation factors.
For more information about configuring change risk calculation, see Assessing the risk for a change request.