The Copy Change function is available on the Change form only when it is in Modify mode. Use this function to copy a request into a new change request. When you use the function, you have options to include different sections of the original change request; for example, Requested For Customer, Impacted Areas, CI/Component Relationships, Related Changes, or Work Info with attachments.
The following fields are populated with information from the change from which you are copying:
- Summary
- Change Type
- Class
- Timing Reason
- Impact
- Urgency
- Priority
- Risk Level
- Lead Time
- Environment
- Reason For Change
- Notes
You can change the information in these fields to reflect the new change. You are also presented with different sections of the change that you can copy.
Important
Users with Change viewer and Change submitter permissions cannot copy a change request.
- From the left navigation pane on the Change form, select Functions > Copy Change.
- On the Copy Infrastructure Change dialog box, click the sections to include in the new change request.
Make modifications to the new request that you are creating (for example, changing its Summary, Notes, Priority, and Timing Reason).

Select the sections that you want to copy.
Depending on the options that you select, the following information is copied to the new change request. The Task Phase settings of the original change request are also copied to the new change request.
| |
---|
Copy Requested For Customer | All information from the Requested For dialog box. |
| |
Copy CI/Component Relationships | All CIs or Components from the Relationship tab. If you select this option and copy a change request that relates to an End of Life CI, the new change request also relates to the End of Life CI. |
| You will be prompted to enter additional information in the Copy Tasks dialog box. For more information, see step 5. |
| All related change requests. Related Infrastructure Change Requests with a Dependent relationship type will be converted to Related To relationships. To keep the dependent relationship, in the Relationship tab, search for the dependent change request, make a new dependent relationship and delete the Related To relationship that were copied. |
Copy Work Info (with attachments) | All Work Info, including attachments. Manually refresh the Work Info on the copied change request to view the copied information. |
When you select Copy Tasks, the Copy Tasks dialog box is displayed.

- Select the tasks that you want to exclude from copying either By Status (Cancelled, and Failed) or by Task Type (Manual, and Automatic).
Depending on the options that you select, the following information is copied to the new change request:
| |
---|
Copy Location Information with Attachments | The following information from the General tab related to Task Location and the Task Attachments, except Command field: - Company
- Region
- Site Group
- Site
- Address
- All related attachments
|
Copy Requester Information | The following information from the Requester tab: - Requester Company
- First Name
- Middle Name
- Last Name
- Phone Number
- Organization
- Department
- Support Organization
- Support Group Name
|
Copy Work Info with Attachments | All information from the Work Info tab including any attachments. |
| All information from the Relationships tab. |
| The following information from the Dates tab is copied: - Schedule start date
- Schedule end date
|
| The following information from the Financials tab: - Calculation Unit type
- Budget Estimated Total Time
|
- (Optional) Click Task Details to overwrite all copied Tasks and to enter values in the following fields:
- Specify a value in the Summary field.
If you specify a summary value, the Summary field of all the new copied tasks uses this value. Otherwise, the Summary field of all the new copied tasks uses the values of the source tasks. - Select the Priority of the task.
- You can enter notes in the Notes field.
- Click OK.
On the Copy Infrastructure Change dialog box, click Start Copy.
Important
The Support Group and Change Coordinator information is not copied to the new change request, and the user's default Support Group and Change Coordinator information is applied to the new change request.
If the Assignee field of the task that is being copied has an invalid value, the Assignee field does not get copied to the new change request.
The copy function can take several minutes to process. All tasks and child tasks related to that task are copied. After the change is copied, the Change form opens in New mode with the newly copied change information in Draft status. Any tasks that are copied are in Staged status.
- Save the new copy of the request, because a copied change request is not automatically submitted.