Removing a SQL Server Availability Group
Before you begin
- You must have a SQL Server Availability Group.
To remove a SQL Server Availability Group
- From the Management Console, navigate to the Availability Group that you want to remove.
- Select Provision > Remove SQL Server Availability Group.
In the General page, populate the following fields, and click Next.
In the Custom Scripts Configuration page, select any pre-provisioning or post-provisioning scripts that you want to run as follows, and click Next.
In the Job Options page, specify any of the following Job options, and click Next.
If the Change Control page displays, populate the following fields, and click Next.
- In the Summary page, review the provisioning information.
To make changes, do the following:- Click Go to to return to the provisioning step that you want to edit.
- Make your changes.
- Click Save and Review to return to the Summary page.
- Specify your verification preferences.
For additional information, see Understanding-pre-verification-tests.- To continue with removing the availability group after the pre-verification tests have been successfully run without manual intervention, select Automatically Continue If All Tests Succeed.
To remove the availability group without having first run the pre-verification steps, select Skip Pre-Verification Tests.
Click Remove SQL Server Availability Group.
A progress page appears followed by a success message upon completion. The SQL Server Availability Group no longer displays under the cluster in the Context Pane.