Limited supportBMC provides limited support for this version of the product. As a result, BMC no longer accepts comments in this space. If you encounter problems with the product version or the space, contact BMC Support.BMC recommends upgrading to the latest version of the product. To see documentation for that version, see BMC AMI Ops Infrastructure 7.1.

Generating threshold charts


Use the following procedures to display various charts of the threshold data for a given metric.

To generate a threshold chart

On the Reporting page, click View Threshold Charts.

A default chart of threshold data for the first instance of the selected metric is displayed in a separate window (as shown in the figure below).

GUID-A66E37C3-8531-42C8-AE39-C523160D2CC3-low.png

The initial chart type is Collected Data, which displays the collected data and recommended threshold values. You can use the date range selectors at the top to adjust the date range for which data is displayed.

To display a different chart type

In the threshold chart window, click the appropriate tab at the bottom for the type of chart that you want to display:


Chart type

Description

Summarized by Weeks

Collected data summarized for each calendar period within each week of the specified date range

Summarized by Calendar Periods

Collected data summarized for each calendar period across all weeks in the specified date range

Exceptions

Number of exceptions that would occur during each hour of a typical week, based on the recommended thresholds

After the initial chart of each type is generated, you can move between the charts for a given instance of data by clicking the appropriate tab at the bottom of the window.

To display a chart for a different instance of data

From the Available Objects list in the chart window, select another instance of data to generate a new chart.

Note

The list of available objects corresponds to the rows of data in the threshold report. Each row in a report is a separate instance of metric data that can be displayed in chart form.

Modifying threshold charts

Use any of the following options to modify a generated threshold chart:

Option

Description

Business Week Display Options

Show or hide one or more calendar periods in the chart.

Display Options

Show or hide the following elements in the chart:

  • Reported value
  • Recommended threshold
  • Severity levels
  • Metrics

Note

The specific options that are available vary according to the chart type.

Chart Settings

Switch between automatic scaling and manual scaling of the Y-axis.

Toggle Data View

Switch between a chart and its underlying data.

To export chart data

Use the following procedure to export the currently displayed chart data to a CSV file for manual processing.

  1. In an open threshold chart window, click GUID-2876E87D-4362-42F7-926E-0A0FC031BF04-low.pngExport Chart Data to CSV.The chart data is displayed in CSV-compatible format in a separate window.

  2. Follow the instructions to export some or all of the chart data to an external application in CSV format.



 