Restarting CICS target regions


To complete the implementation of BBI-SS PAS to CICS communication, do the following steps:

  1. Start each BBI-SS PAS that will communicate with a CICS region (if it is not already active).
  2. Shut down each CICS region that will communicate with a BBI-SS PAS that is already active.
  3. Start each CICS region that will communicate with a BBI-SS PAS.
  4. For each CICS region that communicates with a BBI-SS PAS but for which the procedure in Modifying-the-Program-List-Table-PLT was not performed, manually start BBI-SS PAS-to-CICS communication; use either the SMN2 transaction from within the CICS region or the FST2 transaction from the z/OS console.Refer to Manual-activation-of-BBI-SS-to-CICS-communication for more information.
  5. Ensure that the following messages are issued from each CICS region that will communicate with a BBI-SS PAS: 

    +FT431I SESSION WITH BBI-SS PAS ESTABLISHED

     

    +FT428I CICS MESSAGE INTERCEPT COMPLETED

    The following messages are issued from each CICS region that communicates with a BBI-SS PAS:

    +FT431I SESSION WITH BBI-SS SSID ESTABLISHED+FT806I AutoOPERATOR for CICS initialization started

     

    +FT803I CICS TRANSIENT DATA INTERCEPT STARTED
       +FT428I CICS MESSAGE INTERCEPT START COMPLETED
       +FT809I AutoOPERATOR for CICS initialization complete

    The implementation of BBI-SS PAS to CICS communication is now complete.

 