Adding the NO89 command to a Model Builder Task
Use the following procedure to add NO89 commands to a Model Builder Task for each MLC product or Priced Feature that does not create SMF Type 89 records. After the next scheduled run of the Model Builder Task, your cost models will include cost data for the MLC products or Priced Features that you cite in these NO89 commands.
- From the Cost Analyzer console, click Administration Tools.
In the Administration Tools window, click Manage Model Builder Tasks.The Manage Model Builder Tasks dialog lists all of the tasks that have been defined:
Select the task for which you need to add the NO89 command, and click Modify.The Modify Model Build Task dialog is displayed as shown in the following figure:
On the Modify Model Build Task dialog, click Advanced Options and then select the NO89 Commands tab.The Advanced Options dialog displays as shown in the following sample figure:
In the box, enter the command as follows:
NO89 <productid>[:<featurecode>]=[<cpcsn>:]<lparname>,... | *ALLThe following table defines the value of the variables:
Variable
Description
productID
(required) IBM product number, which is typically a seven-digit number in the form of XXXX-XXX
featureCode
(optional) IBM priced feature number
CPCSN
(optional) CPC serial number
CPCSN can either be the full or partial CPC serial number. The partial CPC serial number is the last four hex digits of the full CPC serial number.
lparName
(required) One or more LPAR names, separated by commas , or *ALL
- When finished, click Accept.The Advanced Options dialog closes.
- In the Modify Model Build Task dialog, click Modify Task.The NO89 command is added to the Model Builder Task.
- In the Manage Model Builder Tasks dialog, click Save Changes to save the Model Builder Task to the server.After the next scheduled run of the Model Builder Task, cost data for the MLC product or the priced feature that does not generate Type 89 records will exist in the cost models.