Contract Summary quadrant
The Contract Summary quadrant displays a chart that compares spending against budgeted amounts for both the current expenditures and the projected total cost of the entire term of the contract.
The following figure shows a sample Contract Summary that displays charts that show the current spend and the projected spend compared to their corresponding budgeted allocations.
Figure: Sample Contract Summary quadrant
Contract Summary legend
# | Description | Details |
---|---|---|
1 | Contract end month with cost difference | The date identifies the month the contract ends and the amount indicates the cost difference between the accumulated Projected Spend amount and the accumulated Budgeted amount. |
2 | Toggle dots | Click the dots to toggle between available chart views. These dots let you switch between the following views:
|
3 | Contract billing month with cost difference | The date identifies the current billing month of the contract and the amount indicates the cost difference between the current spending amount and the current budget amount. |
4 | Year over Year Cost | The amount indicates the difference between what was spent in the current month relative to how much was spent in the same month a year ago. |
5 | Ending date of contract | The date and year of the last month of the contract. |
6 | Starting Date of contract | The date and year of the starting month of the contract. |
7 | Current spend amount | The amount indicates the total MLC product spending from the start of the contract through the current billing month. |
8 | Volume chart of current spend and current budget | The bar chart indicates the cumulative volume level of both the current spending and the current budget amounts. The bar represents the accumulated spending from the start of the contract through the current billing month. The color (whether green or red) indicates whether the current spending is over or under the budgeted amount allocated. |
9 | Current budget | The amount indicates the total budgeted for spending from the start of the contract through the current billing month. |
10 | Contract name | The name assigned to the contract. |
11 | Projected spend | The amount indicates the total MLC product spending from the start of the contract through the end of the contract. |
12 | Volume chart of projected spend and total budget | The bar chart indicates the cumulative volume level of both the total projected spending and the total budget amounts. The bar represents the accumulated spending from the start of the contract through the end of the contract. The color (whether green or red) indicates whether the projected spending is over or under the budgeted amount allocated. |
13 | Total budget | The total amount budgeted for the contract. |
14 | Minimize/maximize control button | A control button to maximize or minimize the chart view. |
The Contract Summary contains an alternative Chart View (MLC Product Summary View) where you can also access hyperlinks to the MLC Product Activity View.
For information about drill-down levels and hyperlinks of the MLC Contract Summary View, see Accessing-the-MLC-Product-Summary-View.