Limited support BMC provides limited support for this version of the product. As a result, BMC no longer accepts comments in this space. If you encounter problems with the product version or the space, contact BMC Support.BMC recommends upgrading to the latest version of the product. To see documentation for that version, see BMC AMI Ops Infrastructure 7.1 .

Specifying time spans for a calendar period


The time spans that you specify in a calendar period definition determine when a calendar period is active.

If the current time and day of the week fall within a time span that is defined in a calendar period definition and that definition is enabled, the calendar period is active.

Use the following procedures to specify time spans in a calendar period definition:

To add a time span

  1. On the CALDEF view, type one of the following commands and press Enter:
    • Add line command to create a time span based on an existing one
    • ADD primary command to create a time span from scratch
  2. On the Add Calendar Time Span dialog, specify a start time, stop time, and one or more days of the week.For more information about completing the Add Calendar Time Span dialog, see the online Help.
  3. Type END on the COMMAND line and press Enter.

To change a time span

  1. On the CALDEF view, type the CHange line command next to the time span that you want to change and press Enter.
  2. On the Change Calendar Time Span dialog, change the time span values as needed.For more information about completing the Change Calendar Time Span dialog, see the online Help.
  3. Type END on the COMMAND line and press Enter.

To delete a time span

On the CALDEF view, type the DELete line command next to the time span that you want to delete and press Enter.

 