Contract Summary quadrant
The Contract Summary quadrant displays a chart that compares spending against budgeted amounts for both the current expenditures and the projected total cost of the entire term of the contract.
The following figure shows a sample Contract Summary that displays charts that show the current spend and the projected spend compared to their corresponding budgeted allocations:
The Contract Summary legend are as follows:
# | Description | Details |
---|---|---|
1 | Budgeted Cost | The total amount budgeted for the contract. |
2 | Volume chart of projected spend and total budget | The bar chart indicates the cumulative volume level of both the total projected spending and the total budget amounts. The bar represents the accumulated spending from the start of the contract through the end of the contract. The color (whether green or red) indicates whether the projected spending is over or under the budgeted amount allocated. |
3 | Projected Under Budget | The amount indicates the cost difference between the accumulated Projected Spend amount and the accumulated Budgeted amount. |
4 | Projected Spend | The amount indicates the total MLC product spending from the start of the contract through the end of the contract. |
5 | Year over Year Cost | The amount indicates the difference between what was spent in the current month relative to what was spent in the same month a year ago. |
6 | Ending Date of contract | The date and year of the last month of the contract. |
7 | Starting Date of contract | The date and year of the starting month of the contract. |
8 | Volume chart of current spend and current budget | The bar chart indicates the cumulative volume level of both the current spending and the current budget amounts. The bar represents the accumulated spending from the start of the contract through the current billing month. The color (whether green or red) indicates whether the current spending is over or under the budgeted amount allocated. |
9 | Current spend amount | The amount indicates the total MLC product spending from the start of the contract through the current billing month. |
10 | Current budget | The amount indicates the total budgeted for spending from the start of the contract through the current billing month. |
11 | Link button | Click to switch the view to show the Product Summary Report. The Contract Summary contains an alternative chart view (Product Summary Report) where you can also access hyperlinks to the Top Contributors Report. |
12 | Minimize/maximize control button | A control button to maximize or minimize the chart view. |
13 | Current Budget indicator | The black line indicates the current budget amount represented in the bar chart. |
14 | Current Under Budget | The amount indicates the cost difference between the current spending amount and the current budget amount. |
15 | Projected Budget indicator | The gray line indicates the projected budget amount represented in the bar chart. |
For information about drill-down levels and hyperlinks of the Product Summary Report, see Accessing-the-Product-Summary-Report.