Preparing the basics for disaster recovery


This section describes the first phase of DR preparation.

Without proper preparation, no DR scenario can be successful.

The preparation phase consists of the following procedures:

  1. Establishing-RMGR-groups
  2. Creating profiles
  3. Maintaining IDCAMS database allocation statements
  4. Obtaining RECON and repository backups
  5. Create-multiple-copies-of-recovery-assets
  6. Verify-recovery-assets


 