Generating a batch report
To generate batch reports through the console
- In the Navigation window, right-click the IMS Applications object.
Select Batch Reports > Resource Savings Batch Report.Application Accelerator submits a batch job to generate the report. When the job completes successfully, Application Accelerator issues message BMCMXO340683I, which indicates the name of the mainframe data set that contains the report. The information is displayed in the BMC Application Accelerator for IMS Savings History window.
To generate batch reports through the CPCBATCH utility
- Identify the report and content that you want to generate:
- The Resource Savings Report, which shows the accumulated savings for the current profile of each job step
- The JOBSTEP History Report, which shows the savings for each execution of each job step for which data is available
- Create JCL to execute the utility.For more information, see CPCBATCH-JCL-requirements.
- Specify control statements in the CPCSYSIN data set.For more information, see the following topics:
- Run the JCL and view the reports.For more information, see Description-of-data-columns-on-the-resource-savings-reports.