Phase 2 job failure - rerunning Phase 2 jobs


This section describes procedures to follow if a failure occurs during Phase 2, and you wish to run the job(s) again (as opposed to restarting the jobs).

  1. Determine what caused the job(s) to fail and correct the situation.
  2. You may need to issue the DB2 TERM UTILITY command if the failed step was a DSNUTILB execution.
  3. Make a copy of the original ARMBSRR-generated JCL as a backup.
  4. Edit the ARMBSRR-generated JCL. Delete all Phase 1 jobs from the JCL.

    Warning

    Important

    Phase 1 jobs precede all Phase 2 jobs in the JCL, and each job contains a comment that indicates its phase. You can easily locate the first Phase 2 job by searching for the phrase PHASE 2 JOB 1 and then delete all JCL prior to that phrase in the file.

  5. Submit the edited JCL, which then reruns Phase 2. It also deletes and reallocates the synchronization file.


 

Tip: For faster searching, add an asterisk to the end of your partial query. Example: cert*

BMC AMI Recovery Manager for Db2 13.1