Managing the BMC AMI Utility Management schedule settings


You can schedule the utility processing criteria for groups of table spaces, indexes, and applications. Use the following procedures to add to, edit, or delete a schedule in the Schedules table.

To add a schedule

  1. In the Product Tools perspective, select or add a BMC AMI Utility Management view.
  2. In the Schedules tab, click Add schedule NW_plus_circle_o.png
  3. in the General tab, complete the following fields:

    Field

    Description

    Type

    Select one of the following types:

    • Applications
    • Table spaces
    • Indexes

    Name pattern

    Enter a name pattern for the group of objects or applications for which you want to create a schedule. You can use the * or % wildcard, or both.

    Partition

    Enter a partition number or specify 0 for all partitions.

    Comment

    (Optional) Enter a comment describing the schedule.

  4. In the Schedule tab, complete the following fields:

     

    Field

    Description

    Utility ID

    Either leave this field blank to include all utility IDs in this schedule or enter a utility ID to limit this schedule to that utility. For more information, see Creating a Utility Status view.

    Apply to BMC AMI Reorg

    Apply to BMC AMI Copy

    Apply to BMC AMI Stats

    Select one or more utilities that you want to schedule.

    Include or Exclude

    Indicate whether to include or exclude the group of objects from processing according to the schedule.

    Monthly

    Weekly

    Select when to perform the processing:

    • On a specific day of each month, or a specific day of a specific month
    • Every day of the month
    • On a specific day each week, or every day of the week

    Start time

    Select a start time for the process.

    Important

    The product does not support starting a process before midnight and completing it the following day. For that scenario, you would need to create two schedules (one ending at 23:59:59 and one beginning at 00:00:00).

    End time

    Select an end time for the process.

  5. Click OK .
    NG_plus_circle_dgreen.png is displayed next to each added schedule.
  6. Click Save Changes NW_floppy.png to save all the changes to the BMC AMI Utility Management view.

To edit schedules

You can edit multiple criteria, exceptions, schedules, and durations before you save all the changes to the BMC AMI Utility Management view in one action.

  1. In the Product Tools perspective, select a BMC AMI Utility Management view.
  2. In the Schedules table, select a schedule that you want to edit and click Edit schedule NW_pencil_adapt.png.
    The schedule that you are editing is displayed at the top of the dialog box. 
  3. In the Edit BMC AMI Utility Management Schedule dialog box, edit the values in the General and Schedule tabs.
  4. (Optional) Edit additional schedules using the Previous schedule NW_arrow_up_circle.png and Next schedule NW_arrow_down_circle.png arrows to navigate to another exception.
  5. When you have completed your edits, click OK
    NG_pencil_adapt_blue.png is displayed next to each edited schedule.
  6. To verify the edited schedule, you can reset the changes, by selecting one or more edited schedules and clicking NW_refresh.png.
  7. (Optional) You can now edit the Criteria, Exceptions, and Durations settings.
  8. Click Save Changes NW_floppy.png to save all the changes to the BMC AMI Utility Management view.

    Important

    Next time that you select an edited schedule, the Last update field will show the user ID and timestamp of the last update to the schedule.

To delete schedules

  1. In the Product Tools perspective, select a BMC AMI Utility Management view.
  2. In the Schedules table, select one or more schedules for deletion.
  3. Click Delete schedules NW_minus_circle_o.png.
    NW_minus_circle_red.png is displayed next to each schedule that you selected to delete.
  4. Verify the schedules that you selected to delete, you can undo the deletions, by selecting one or more selected schedules and clicking NW_refresh.png.
  5. Click Save Changes NW_floppy.png to confirm the deletions from the BMC AMI Utility Management view.

 

Tip: For faster searching, add an asterisk to the end of your partial query. Example: cert*