You can schedule the utility processing criteria for groups of table spaces, indexes, and applications. Use the following procedures to add to, edit, or delete a schedule in the Schedules table.
To add a schedule
New console
- In the Product Tools perspective, select or add a BMC AMI Utility Management view.
- In the Schedules tab, click Add schedule
. in the General tab, complete the following fields:
| |
---|
| Select one of the following types: - Applications
- Table spaces
- Indexes
|
| Enter a name pattern for the group of objects or applications for which you want to create a schedule. You can use the * or % wildcard, or both. |
| Enter a partition number or specify 0 for all partitions. |
| (Optional) Enter a comment describing the schedule. |
In the Schedule tab, complete the following fields:
| |
---|
| Either leave this field blank to include all utility IDs in this schedule, or enter a utility ID to limit this schedule to that utility. For more information, see Creating-a-Utility-Status-view. |
Apply to BMC AMI Reorg Apply to BMC AMI Copy Apply to BMC AMI Stats | Select one or more utilities that you want to schedule. |
| Indicate whether to include or exclude the group of objects from processing according to the schedule. |
| Select when to perform the processing: - On a specific day of each month, or a specific day of a specific month
- Every day of the month
- On a specific day each week, or every day of the week
|
| Select a start time for the process. Important The product does not support starting a process before midnight and completing it the following day. For that scenario, you would need to create two schedules (one ending at 23:59:59 and one beginning at 00:00:00). |
| Select an end time for the process. |
- Click OK .
is displayed next to each added schedule. - Click Save Changes
to save all the changes to the BMC AMI Utility Management view.
Classic console
- In the Product Tools perspective, select or add an NGT Utility Management view.
In the Schedules tab, click Add schedule
.
Tip
You can also right-click in the table to select this action.
in the General tab, complete the following fields:
| |
---|
| Select one of the following types: - Applications
- Table spaces
- Indexes
|
| Enter a name pattern for the group of objects or applications for which you want to create a schedule. You can use the * or % wildcard, or both. |
| Enter a partition number or specify 0 for all partitions. |
| (Optional) Enter a comment describing the schedule. |
In the Schedule tab, complete the following fields:
| |
---|
| Either leave this field blank to include all utility IDs in this schedule, or enter a utility ID to limit this schedule to that utility. For more information, see Creating-a-Utility-Status-view. |
Apply to NGT Reorg Apply to NGT Copy Apply to NGT Stats | Select one or more utilities that you want to schedule. |
| Indicate whether to include or exclude the group of objects from processing according to the schedule. |
| Select when to perform the processing: - On a specific day of each month, or a specific day of a specific month
- Every day of the month
- On a specific day each week, or every day of the week
|
| Select a start time for the process. Note The product does not support starting a process before midnight and completing it the following day. For that scenario, you would need to create two schedules (one ending at 23:59:59 and one beginning at 00:00:00). |
| Select an end time for the process. |
- Click OK .
is displayed next to each added schedule. - Click Save Changes
to save all the changes to the NGT Utility Management view.
To edit schedules
You can edit multiple criteria, exceptions, schedules and (BMC.DB2.SPE2201) durations before you save all the changes to the BMC AMI Utility Management view in one action.
New console
Classic console
To delete schedules
New console
- In the Product Tools perspective, select a BMC AMI Utility Management view.
- In the Schedules table, select one or more schedules for deletion.
- Click Delete schedules
.
is displayed next to each schedule that you selected to delete. - Verify the schedules that you selected to delete, you can undo the deletions, by selecting one or more selected schedules and clicking
. - Click Save Changes
to confirm the deletions from the BMC AMI Utility Management view.
Classic console
- In the Product Tools perspective, select an NGT Utility Management view.
- In the Schedules table, select one or more schedules for deletion.
- Click Delete schedules
.
is displayed next to each schedule that you selected to delete. - Verify the schedules that you selected to delete, you can undo the deletions, by selecting one or more selected schedules and clicking
. - Click
to confirm the deletions from the NGT Utility Management view.