Limited support BMC provides limited support for this version of the product. As a result, BMC no longer accepts comments in this space. If you encounter problems with the product version or the space, contact BMC Support.BMC recommends upgrading to the latest version of the product. To see documentation for that version, see ALTER and BMC AMI Change Manager for Db2 13.1.

Generating a baseline report


Use the following procedure to generate a baseline report. The baseline report contains information that is specific to a baseline, including the DDL for the objects in the baseline.

To generate a baseline report

  1. On the BMC AMI Change Manager for Db2 Main Menu, select Baselines, and press Enter.
  2. On the Baseline Action Menu, type the Baseline name and select Generate a report for a Baseline. Then, press Enter.

    Note

    If you do not know the name of the baseline, you can type a wildcard pattern for the Baseline name and press Enter. The Baseline Selection List is displayed. Type S in the Act column adjacent to the baseline for which you want to generate a report, and press Enter. The Baseline Report Panel 1 is displayed.

  3. On the Baseline Report Panel 1, select the Run Type and press Enter.
  4. On Baseline Report Panel 2 panel, specify the data set names to be used in the report.
    1. (Batch run type) Type the data set name for the JCL that is generated by this process.
    2. Type the data set name for the Report that is generated.
    3. Type one of the following options for Diagnostics:
      • (Foreground run type) To display the diagnostics on the terminal, type TERM.
      • To write the diagnostics to a sequential file, type the name of the data set.
      • To write the diagnostics to a print data set, type SYSOUT.
    4. (Foreground run type) If you specified SYSOUT in Step 4.c, specify the SysoutClass.
  5. Select your options for generating the report.
    1. To create the input, select one of the following options:
      • (Foreground run type) Type S to select Create Input.
      • (Batch run type) Type S to select Create JCL.
    2. To review or modify input to the process, select one of the following options:
      • (Foreground run type) Type S to select Edit Input.
      • (Batch run type) Type S to select Edit JCL.
    3. To create the baseline, select one of the following options:
      • (Foreground run type) Type S to select Run Report.
      • (Batch run type) To submit the batch JCL, type S to select Submit JCL.
    4. To edit the report, type S to select Edit Report.
    5. Press Enter.

 