Defining or editing a Pause Baseline Calculation Period


You need to define or edit a pause baseline calculation period.

To define or edit a Pause Baseline Calculation Period

Warning

Note

When a Pause Baseline Calculation Period is edited for the first time, subsequent operations performed (such as create, edit, or delete) on Baseline Pause Periods are not effective until the Rate process is restarted.

  1. Go to Options> Administration> Advanced> Baseline> Edit.
  2. Click the relevant options:
  3. For a new Pause Baseline Calculation Period, click Addunder Pause Baseline Calculation.
    • To edit an existing Pause Baseline Calculation Period, click Edit. After making the required changes, click Update. The system updates the Pause Baseline Calculation Period and returns to the Baseline Freeze Point Administration screen.
  4. In the Pause Baseline Calculation Period screen, select the monitor instance.
  5. Group - Select Groupto include all the instances in the group.
    • SLO - Select SLO Group to include all instances from the SLO group.
    • Device - Select Device to include all the instances associated with the device.
    • Monitor Type - Select Monitor Type to include all instances of the monitor type.
    • Monitor Instance - Select Monitor Instance to add a single monitor instance.
  6. Specify the Pause Baseline period.
    • From time - Specify the start time for the pause period.
    • To time - Specify the end time for the pause period. Select Indefinite to stop a particular baseline calculation.
  7. Click Add.

 

Tip: For faster searching, add an asterisk to the end of your partial query. Example: cert*