Scheduling a rollout
To start a rollout after all configurations
After all the configuration of a rollout is defined and it is assigned to its targets and its schedule specified, it can be launched:
- Select Edit > Start Rollout .
The rollout is launched immediately ignoring any schedule that can be defined for it.
To schedule the rollout at a given time and date
In the Core Setup Configuration window, ensure that the Configure a custom schedule for this rollout (default is one immediate execution) box is selected. Then, after the Targets & Accounts window, the Schedule window appears.
- Select the Validity tab.
- Define in the Execution Date box at what moment the rollout is to be launched for the first time (for example, at the next device startup).
- Define in the Termination box when the rollout is to be run for the last time (for example, stop after 5 executions).
Select the Frequency tab.
- Click Finish .
The rollout is now defined and scheduled to be executed at the specified time.