Removing DBDs and PSBs from a project


To remove DBDs and PSBs from an existing project in BMC AMI Change Manager for IMS, complete the following steps.

  1. From the main screen, select the Projects tab.
  2. Using the search box, select an existing project from which you want to remove the DBDs or PSBs.
  3. The left-hand side pane displays a list of DBDs and PSBs associated with that project.
  4. Select the DBDs and PSBs that you want to remove.
  5. Click Remove DBD/PSB from this project




 

Tip: For faster searching, add an asterisk to the end of your partial query. Example: cert*