Recommendation for managing release requests

As with BMC Change Management, the Release Management module is role-based. What applications you can access, and how much information you can view or modify is dependent upon your role. As the Process Flow Status bar steps you through the milestones of a release request, different roles perform different tasks. The Release Coordinator creates the release request at the Initiate milestone, the Release Approver approves the release at the Build milestone, and the Activity Assignee completes the activity at the Deployment milestone.

Note

Defining approvals at the Build milestone is a recommendation. However, approvals can be defined at each milestone of the Release Management process.


Using the Process Flow Status bar in the milestones of a release request

Click the following figure to expand it.

How each person uses Release Management depends on their role. The following figure illustrates the different Release Management support staff roles. It also shows where each role fits into the milestones of the release request lifecycle.


Release Management support and management roles

Click the following figure to expand it.

Recommendation

To simplify the release request process, the following table navigates you through the BMC Change Management documentation. It provides a map of BMC recommendation that you should follow, when you use the Release Management module.

Note

Approvals might not apply to all milestones in a release request. For example, you see a Build approval if the application administrator mapped an approver to the Build approval phase.


Recommendation for managing release requests

Milestone

Role and task

For more information

1a
Initiate

Release Coordinator creates the release request, change request, and activity.

Initiate milestone - Creating release requests

1b
Initiate

CAB approves the release request.

2a
Planning

Release Coordinator plans release request, uses Change Calendar to check for conflicts.

  1. Reviews Change Calendar.
  2. Enter start and end dates.

Planning milestone - Planning and scheduling the release request

2b
Planning

CAB approves the release request.

3a
Build

Release Coordinator oversees the release builds.

Build milestone - Building a controlled environment for the release

3b
Build

CAB approves the release request.

4a
Test

Release Coordinator oversees the testing of the new service, to make sure CIs meet specifications and requirements.

Test milestone - Testing the release

4b
Test

CAB approves the release request.

5a
Deployment

Release Coordinator rolls release out to the business. Starts phased or non-phased deployment of release.

5b
Deployment

CAB approves the release request.

5c
Deployment

Change Manager executes change request in its Deployment phase.

Deployment milestone - Rolling out the release to the business

5d
Deployment

Task Implementer executes task in its Deployment phase.

5e
Deployment

Activity Assignee executes task in its Deployment phase.

6
Closed

Release Coordinator completes the change request.

Close Down milestone - Completing release requests