User acceptance testing

Before you can promote the staging server, you must perform the following user acceptance testing (UAT) tasks:

  1. Make a backup of the upgraded staging server database.
    This backup is called the pre-UAT backup.
  2. Conduct your UAT using your test cases.
  3. If an issue arises:
    1. Identify a solution, or work with BMC Support to identify a solution.
    2. Apply any fixes to the server, and then validate the fixes.
    3. Make a copy of the fixes for use later.
  4. Complete all UAT tasks and obtain sign-off.
  5. Revert to the pre-UAT backup.
  6. Apply any fixes that were required during UAT.
  7. Work with the database administrator responsible for the staging server to back up the database.
    This backup is called the UAT-Verified-Clean backup.
  8. If desired, run an additional test to validate that fixes have been applied correctly.

    Note

    If no issues arise, the pre-UAT backup becomes the UAT-Verified-Clean backup.

  9.  Restore the staging server to the UAT-Verified-Clean backup.
    After the upgrade is validated on the staging server, restore the system to the UAT-Verified-Clean backup. This ensures that any testing data used during the validation is removed and that the staging server is in a clean state for the delta data migration.
  10. Prepare the destination server for delta data migration.
    After the upgrade is complete and customizations are reapplied, the environment is ready for delta data migration.