Upgrading the Infrastructure Management server in application high-availability mode

Use this topic to understand the process for upgrading the Infrastructure Management server in application high-availability mode.

Before you begin

Review the prerequisites for upgrade at Preparing for the Infrastructure Management upgrade.

To upgrade Infrastructure Management in application high availability mode

  1. Stop the secondary Infrastructure Management server before you proceed with the upgrade. 
    For more information, see Starting and stopping the TrueSight Operations Management components.
  2. Upgrade the primary Infrastructure Management server.
  3. Stop the primary Infrastructure Management server.
  4. Upgrade the secondary Infrastructure Management server.
  5. Stop the secondary Infrastructure Management server.
  6. Start the primary Infrastructure Management server.
  7. Start the secondary Infrastructure Management server.